Comcast, Dunellen's newest service provider has begun underground work to install fiber lines prior to their cable and internet services becoming available throughout the Borough. Minor traffic diversions are possible. Please note that Comcast will not be disturbing any newly paved roads.
For any issues or concerns, please contact Ronald Boogaard at Comcast at (609) 947-0066 or [email protected].
Anticipated Schedule
Week of November 4
- Grove Street
- New Market Road
- Prospect Avenue
- Gertrude Terrace
- South Avenue
- Walnut Street
- Whittier Avenue
Week of November 11
- Columbia Street
- S. Washington Avenue
- New Market Road
- Orange Street
- Penfield Place
Week of November 18
- Grove Street
- New Market Road
- Oak Parkway
- Orange Street
- Penfield Place
- Prospect Avenue
- S. Washington Avenue
- Walnut Street
Week of November 25
- Fairview Avenue
- Penfield Place
- Pulaski Street
- S. Madison Avenue
- S. Washington Avenue
- Walnut Street
Week of December 2
- Center Street
- Fairview Avenue
- Prospect Avenue
- Walnut Street
- Whittier Avenue
Week of December 9
- Dunellen Avenue
- Front Street
- Jackson Avenue
- Mountain View Terrace
- N. Washington Avenue
- Second Street
- Third Street
Week of December 16
- First Street
- Dunellen Avenue
- Front Street
- N. Washington Avenue
Week of December 23
During the week of December 23, Comcast will be pulling cable and setting vaults. No major construction will occur. Cable and vault work will take place on Monday, December 23, Thursday, December 26, and Friday, December 27. No work will be taking place on Christmas Eve or Christmas Day.
Monday, December 23
- High Street
- Walnut Street
- Pulaski Street
- Center Street
- Madison Avenue
- South Avenue
- Third Street
- Jackson Avenue
- Mountainview Terrace
- N. Washington Avenue
Thursday & Friday, December 26 & 27
- First Street
- Second Street
- Fourth Street
- Jackson Avenue
- N. Washington Avenue
January 2 & 3
During the week of December 30, Comcast will be performing their full scope of work on Thursday, January 2 and Friday, January 3 on the following streets:
- Dunellen Avenue
- Jackson Avenue
- Lincoln Avenue
- First Street
- Fourth Street
- N. Washington Avenue
Week of January 6
- Dunellen Avenue
- Jackson Avenue
- Front Street
- N. Washington Avenue
Week of January 13
- First Street
- Second Street
- Third Street
- Dunellen Avenue
- Front Street
- Lincoln Avenue
- Jackson Avenue
- Mountainview Terrace
- N. Washington Avenue
January 18 & Week of January 20 (Starting on Tuesday, January 21)
- First Street
- Lincoln Avenue
Week of January 27
- N. Washington Avenue
- S. Washington Avenue
- Week of February 3
- Dunellen Avenue
- First Street
- Front Street
- N. Washington Avenue
Week of February 10
Comcast will be splicing existing cables with minimal construction work taking place.
- Kline Place
- Jadach Drive
- Pearl Place
- Front Street
- Dunellen Avenue
- First Street
- Second Street
- Jackson Avenue
- Jefferson Avenue
- N. Washington Avenue
Week of February 17
Comcast will be splicing existing cables with minimal construction work taking place.
- Kline Place
- Jadach Drive
- Pearl Place
- Front Street
- Dunellen Avenue
- First Street
- Second Street
- Jackson Avenue
- Jefferson Avenue
- N. Washington Avenue
Week of February 24
Comcast will be splicing existing cables with minimal construction work taking place.
- Kline Place
- Jadach Drive
- Pearl Place
- Front Street
- Dunellen Avenue
- First Street
- Second Street
- Jackson Avenue
- Jefferson Avenue
- N. Washington Avenue
Week of March 3
Comcast will be conducting minimal construction on the following roads.
- Dunellen Avenue
- First Street
- Front Street
- Jackson Avenue
- Jefferson Avenue
- N. Washington Avenue
- Second Street
Week of March 10
Comcast will be conducting minimal construction on the following roads.
- Dunellen Avenue
- First Street
- Front Street
- Jackson Avenue
- Lincoln Avenue
- N. Washington Avenue
- Second Street
Week of March 17
Comcast will be conducting minimal construction on the following roads.
- Dunellen Avenue
- First Street
- Front Street
- Jackson Avenue
- Lincoln Avenue
- N. Washington Avenue
- Second Street
- Third Street
Week of March 24
Comcast will be conducting minimal construction on the following roads.
- Fourth Street
- New Market Road
- Oak Parkway
- S. Washington Avenue
- Walnut Street
Week of March 31
Comcast will be conducting minimal construction on the following roads.
- High Street
- Lehigh Street
- Oak Parkway
- Prospect Avenue
- S. Madison Avenue
- S. Washington Avenue
- Walnut Street
Week of April 7
Comcast will be conducting minimal construction on the following roads.
- High Street
- Lehigh Street
- Oak Parkway
- Prospect Avenue
- S. Madison Avenue
- S. Washington Avenue
- Walnut Street
Week of April 14
Comcast will be conducting restoration work and minimal construction on the following roads.
- Fourth Street
- High Street
- Jackson Avenue
- Lincoln Avenue
- N. Washington Avenue
- Prospect Avenue
- Third Street
- Walnut Street
Week of April 21
Comcast will be conducting minimal construction on the following roads.
- Dunellen Avenue
- Front Street
- High Street
- Jackson Avenue
- Jefferson Avenue
- Mountainview Terrace
- N. Washington Avenue
- Pulaski Street
- South Avenue
Week of April 28
Comcast will be conducting minimal construction on the following roads.
- Fourth Street
- Hall Street
- N. Washington Avenue
- Pulaski Street
- South Avenue
- Third Street
- Walnut Street
Week of May 5
Comcast will be conducting minimal construction on the following roads.
- Fourth Street
- High Street
- N. Washington Avenue
- Pulaski Street
- Second Street
- South Avenue
- South Madison Avenue
- Third Street
- Walnut Street
Week of May 12
Comcast will be conducting minimal construction on the following roads.
- Front Street
- N. Washington Avenue
- Second Street
Week of May 19
Comcast will be conducting minimal construction on the following roads.
- N. Washington Avenue
- Second Street
Week of May 26
Comcast will be conducting minimal construction on the following roads.
- Fourth Street
- N. Washington Avenue
- North Avenue
- Bound Brook Road
- High Street
- Pulaski Street
Week of June 9
Comcast will be conducting minimal construction on the following roads.
- Walnut Street
- N. Washington Avenue
- Mountain View Terrace
- High Street
- Pulaski Street
Week of June 23
Comcast will be conducting minimal construction on the following roads.
- Walnut Street
- Oak Parkway
- Penfield Place
- Orange Street
- Columbia Street
- Kline Place
- Maple Avenue
Wednesday, July 2
Comcast will be conducting road restoration work on the following roads.
- Orange Street
- Penfield Place
- S. Washington Avenue
- New Market Road
- Oak Parkway
Thursday, July 3
Comcast will be conducting road restoration work on the following roads.
- Kline Place
- Whittier Avenue
- Center Street
- New Market Road
- Bache Place
- Fairview Avenue
- Lehigh Street
Week of July 14
Comcast will be conducting restoration work on the following roads.
- First Street
- Second Street
- Third Street
- Dunellen Avenue
- Front Street
- Jackson Avenue
- Jefferson Avenue
- N. Washington Avenue
Completed Underground Conduit & Vault Placement
- Columbia Street
- Orange Street
- Penfield Place
- Gertrude Street
- Jadach Drive
- Kline Place
- Pearl Place
- Kennedy Court